Most downtime programs start in a login. The plant needed a reason and a clock. It got a platform.
A stop is what happened. The dashboard is someone else’s story about it. Get the stop first.
Four kinds of stop
Breakdown: it should run and it cannot. Changeover: you chose to stop. Micro-stop: jams and short waits that never get written down. Quality hold: it could run and you will not let it.
Keep those in one bucket called “down” and every meeting is a fight about words. Split them, then spend money on the biggest one.
- Breakdowns want parts, skill, and a history.
- Changeovers want fixtures, kits, and a clock from last good part to next good part.
- Micro-stops want someone standing at the cell for a day.
- Quality holds want first-article that does not park a machine for an hour.
What a 20% cut actually means
Pick a baseline week with the same shifts. Count minutes in the four buckets. The 20% has to come from one of them. “We will be more careful” is not a lever.
Small plants usually win first on changeover and waits. Breakdowns look serious. Waits look like nothing and eat the week.
When the clipboard is the problem
Paper is fine until Tuesday, when nobody’s numbers match. That is when a small log is worth building: time, machine, code, who. A plant-wide MES is still the wrong first product. Shrink the codes, then log them. Do not digitize a list of twenty reasons nobody uses.
One cell, one week, in minutes
Mill 2, day shift, five days. Breakdown: 40 minutes, one tool. Changeover: 6 hours. Micro-stops nobody had been writing down: 3 hours, mostly a feeder. Quality hold: 90 minutes waiting on a check in another bay. The meeting had been about the tool. The hours were in the changeover and the walk.
They staged the next job’s tools during the last part and moved the first piece to the cell. They did not buy a downtime suite. The following week those two buckets were the only ones on the board. That is a reduction program: a split, a winner, a change you can see in minutes.
This week
- 01
Split last week into four buckets
Breakdown, changeover, micro-stop, quality hold. Minutes, not a story. If two people disagree on the words, fix the words before you buy anything.
- 02
Circle the biggest bucket
The 20% has to come from that one. “Be more careful” is not a lever. Changeover and waits are where small plants usually win first.
- 03
Run a paper log for two weeks
Time, machine, code, who. If people will not mark five codes on paper, they will not mark them in an app.
- 04
Only then decide on software
A small log you own, after the codes are real. A plant-wide system on a list nobody uses will digitize the argument.
Common mistakes
Starting in a login
The plant needed a clock and a reason. A platform is a later purchase. Get the stop first, on paper, where you can still change the list.
One bucket called down
Breakdown, changeover, micro-stop, and a quality hold need different money. Mixed together, every meeting is a fight about vocabulary.
Key takeaways
- Name the kind of stop before you name the software.
- A 20% cut has to come from one bucket you already timed.
- Paper for two weeks is the spec. Shrink the codes, then log them.
If you already have two weeks of stops on paper and you want a log the shop can keep, send that list. If you do not have the list, that is the work — not a quote for another mill.
Questions
- How long before software is worth it?
- Two weeks on one cell. If people will not tap five codes on paper, they will not tap them in an app either. When the paper matches reality, a small log is the next spend — not a factory system.
- Which stop should we attack first?
- The biggest pile of minutes, which is often changeover or waiting, not the crash that has a photo. Breakdowns look serious. Waits eat the week.